Skip to content
Local green power

Floating solar park Zaltbommel

LocationZaltbommel
Capacity4,683 panels · 2.6 MWp
StatusOperational
Design & permits
Construction
Supply
Maintenance & monitoring

On the 5th of December, 2022, Solinoor and Stichting Future Energy Zaltbommel signed the contract for the floating solar park Zaltbommel on a water retention pond. The construction was initiated at the end of Q2 2023 and the floating solar park was operational and commissioned at the beginning of October 2023. In total 4,683 solar panels were installed with a total capacity of 2.6 MWp. The produced energy will be used to power the business park. By using the water area of the retention pond in this industrialised zone, additional renewable energy can be generated to make the business park more sustainable.

Retention pond and business park in Zaltbommel before construction
Zaltbommel, Gelderland

Project overview

4,683solar panels
2.6 MWptotal capacity
Oct 2023operational
4 monthsconstruction time
Dual usefloating solar

Zaltbommel, Gelderland

Project phase & milestones

From contract signature to a park that shrugs off snow and ice, in a little over a year.
Contract signing for the floating solar park Zaltbommel
5 December 2022

Contract signed

On December 5, 2022, Solinoor and Coöperatie Duurzaamheid Bedrijventerreinen Zaltbommel signed the contract for the floating solar park Zaltbommel. By signing the agreement, we can work cooperatively to reach our sustainable aspirations by making industries more sustainable with the use of renewable energy.

Transformer station being placed at the floating solar park Zaltbommel
2 June 2023

Placing transformer station

Over the previous months, the team has worked hard to finalise the preparations for the construction of the floating solar park. Now that the construction of the solar park has been initiated, we can now celebrate our first major milestone with the transformer station being installed.

Crane placing concrete anchor blocks from a pontoon at Zaltbommel
10 July 2023

Anchoring

In preparation for the floating solar island to be placed, the anchoring works have been done. By placing over 90 concrete blocks, a robust foundation has been laid out to keep the floating solar park in place in all weather conditions.

Floating solar platform being assembled on the water
14 August 2023

Start floating platform

The construction of the floating solar platform has been started whereby the floaters, PV panels, and DC cables are assembled. After the assembly of the arrays, the block which is then moved into the water and anchored in place.

Floating panel blocks being moved onto the retention pond
23 August 2023

Platform placement

The assembled blocks of the floating solar platform are moved to its designed locations. Once at its location, the blocks are anchored in place and connected together to form one solid platform.

Completed floating solar platform on the retention pond
8 September 2023

Platform complete

The floating solar platform is now fully built and anchored in place. The final steps are connecting the last few cables with the inverters and transformer station, removal of the construction site-setup, and finalising the details of the complete system.

Aerial view of the completed floating solar park Zaltbommel
5 October 2023

Floating solar park operational

Since the beginning of October 2023, the floating solar park is fully operational and producing renewable energy. In roughly 4 months, the entire construction of this project has been completed.

Floating solar park Zaltbommel covered in frost
19 January 2024

Snow and ice

After several severe autumn and winter storms, the floating solar park shows its resilience yet again in snow and ice weather conditions.

Have a site in mind?

Water, residual land or roof: we are glad to look at whether there is a project in it.